- Post Tag
May 2019
May 2019 Updates...
The second delivery of the 'building blocks' for the main structure of the house......
Michael
26th May 2019
A final day of work this week, in my absence, to add the last layer in...
Michael
24th May 2019
Tuesday 21st May - I am only going to work until lunchtime as I am flying...
Michael
21st May 2019
Rain held off all day and a lot progress made putting in the infill and completing...
Michael
20th May 2019
Friday 17th May - Rain stopped play today. It was too wet to work we would...
Michael
17th May 2019
Thursday 16th May - Pipework completed and sewer pipes all glued together, no going back....
Michael
17th May 2019
Loading more posts...
More Tags…
April 2019 (7)
April 2024 (3)
Architect (4)
August 2019 (7)
Bathrooms (5)
Bedrooms (6)
December 2022 (1)
December 2023 (2)
Decking (4)
Delivery (7)
Drainage System (1)
Eco-Products (1)
Eco-Store (2)
External Walls (17)
Foundations (17)
Gallery (69)
Groundworks (14)
Internal Walls (8)
January 2020 (1)
January 2024 (1)
July 2019 (12)
July 2023 (1)
July 2024 (1)
June 2019 (14)
June 2024 (1)
Kitchen (2)
Lessons (4)
Living Room (3)
March 2024 (1)
May 2019 (13)
November 2019 (1)
October 2019 (6)
Pipework (3)
Pre-Build (3)
Roof (17)
SARL French Plans (1)
September 2019 (1)
September 2020 (2)
September 2023 (1)
Setbacks (9)
Veranda (9)
Video (3)
Wardrobes (1)
Weather Damage (5)
Windows (7)