Delivery Updates...
Taking note of a lesson learnt, Tony was on site to meet the cladding panels delivery....
Michael
23rd December 2023
The windows and patio doors have arrived in readiness for fitting in Spring 2020......
Michael
11th January 2020
Delivery Day 4 - Saturday 13th July. The final pieces have arrived - the metal roof...
Michael
13th July 2019
Delivery of the third & final load for the main structure of the house in readiness...
Michael
17th June 2019
The second delivery of the 'building blocks' for the main structure of the house......
Michael
26th May 2019
After yesterday’s issue with the crane bursting a hydraulic pipe, it was down to waiting for...
Michael
14th May 2019
Loading more posts...
More Tags…
April 2019 (7)
April 2024 (3)
Architect (4)
August 2019 (7)
Bathrooms (5)
Bedrooms (6)
December 2022 (1)
December 2023 (2)
Decking (4)
Delivery (7)
Drainage System (1)
Eco-Products (1)
Eco-Store (2)
External Walls (17)
Foundations (17)
Gallery (69)
Groundworks (14)
Internal Walls (8)
January 2020 (1)
January 2024 (1)
July 2019 (12)
July 2023 (1)
July 2024 (1)
June 2019 (14)
June 2024 (1)
Kitchen (2)
Lessons (4)
Living Room (3)
March 2024 (1)
May 2019 (13)
November 2019 (1)
October 2019 (6)
Pipework (3)
Pre-Build (3)
Roof (17)
SARL French Plans (1)
September 2019 (1)
September 2020 (2)
September 2023 (1)
Setbacks (9)
Veranda (9)
Video (3)
Wardrobes (1)
Weather Damage (5)
Windows (7)