An eco-friendly new build in South West France

An eco-friendly new build in South West France

Utilities and Pipework – 16th May 2019

Groundworks | Pipework

Thursday 16th May 2019

Pipework completed and sewer pipes all glued together, no going back. The sewer pipe glue set almost instantaneous so the pipes had to be orientated first time. All the water pipework was installed with “Gaine”  (protective sleeve) to stop the concrete attacking the pipework.

The pipework under the slab will save a lot of effort so the plumbing is effectively almost complete including a cold water feed outside. The foundation infill was being brought up to level ready for the membrane and insulation to be installed.

The electricity supply “gaine” was installed through the foundation wall. Additional “gaine” was installed to carry outside power and lighting cables later.

Lessons Learnt...

  • Do not make assumptions about where to put the electricity consumer unit, it cannot be in a cupboard and must be 1.0 to 1.8 metres above the floor. I had to rethink that one.

Gallery | May 2019

More Posts...

Quick Search...

Get in Touch...

If you have any questions or general enquiries, please send us a message...

First Name *
Surname *
Email *
Subject *
Message *
* Field is required