Bathroom Walls – 23rd & 24th July 2019

Build | Internal Walls – Bathroom & En-Suite

Tuesday 23rd & Wednesday 24th July 2019

The weather is beautiful at the moment with air temperatures in the mid-late 30’s. However, working in the direct heat of 40°C + is neither comfortable nor advisable so we restricted our work on Tuesday and Wednesday to the mornings only.

This still gave us sufficient time to build the internal wall separating the bathroom / second bedroom and the wall for the en-suite bathroom in the main bedroom.